Southchurch Library could be refurbished, rebuilt, moved to the community college or moved elsewhere, at £150,000 to £750,000. Cabinet decides on 17 December.

Southend Council has four options for the future of Southchurch Library, costing from about £150,000 to £750,000. Most of the 712 people who answered its consultation want the library to stay where it is.

A report for councillors sets out the four choices and the results of the survey. The council’s Place Overview and Scrutiny Committee discusses it on Thursday 3 December. Cabinet then considers recommendations on Thursday 17 December (meeting papers).

No decision has been made, the council said in a release on 25 November. The committee will not be asked to pick a preferred option.

Overview

  • What: the council is deciding whether to refurbish, rebuild or move Southchurch Library.
  • Cheapest option: a move to Southend City Community College on Ambleside Drive, at about £150,000.
  • What residents said: 656 respondents said it was very important the library stays accessible locally.
  • When: scrutiny committee on 3 December, Cabinet on 17 December 2026.

The four options

The figures below come from the report to the scrutiny committee (report).

Option Estimated cost What the report says
Refurbish the existing building About £325,000 or more Only “a short-term life extension”: the core would still be a 1970s portable building
New build on the current site £500,000, plus about £40,000 demolition and a £50,000 contingency Supported by the consultation, but the library would be disrupted during building work
Move to Southend City Community College About £150,000 The cheapest and least disruptive, about 0.6 miles or a 13-minute walk away
Another location £700,000 to £750,000 for Southchurch Park or Bournes Green Park Both park sites carry “significant planning risk” over the loss of open space

The new build and park figures leave out fitting out the building and running a temporary library meanwhile.

Bar chart of the estimated capital cost of each Southchurch Library option: move to Southend City Community College £150,000; refurbish the 1972 building £325,000; new build on the current site £590,000 including £40,000 demolition and a £50,000 contingency; build in Southchurch Park or Bournes Green Park up to £750,000.
Chart by Southend Today. Source: Southend-on-Sea City Council report to Place Overview and Scrutiny Committee, 3 December 2026.
Share this chartFacebookWhatsAppX

Only the college move is already budgeted. The council’s capital programme holds £350,000 for the college, funded by borrowing, and £150,000 of that is for a possible library. Every other option would need extra borrowing, the report says.

Residents also suggested other buildings. The most common was the empty double-fronted shop on Southchurch Road that was formerly Izod’s. Others named the former college site on Southchurch Boulevard and The Plaza Centre. Using a building the council does not own would mean a lease or a purchase, the report says.

Why the building needs a decision

Southchurch Library opened on 9 September 1972 at the junction of Southchurch Road and Lifstan Way. It is a single-storey prefabricated timber building with a flat felt roof and single-glazed windows.

It was meant as a temporary home after the library moved out of Southchurch Hall. Buildings of its type were usually designed to last 20 to 30 years.

A condition survey in December 2023 found it “in very poor condition”. It recommended thinking about rebuilding the library entirely. The survey put remedial work at about £250,000, mostly on the timber structure, windows and fire safety. A likely roof replacement takes that to about £325,000. Asbestos, rated low risk, would add to the cost.

The library had about 30,000 visits in 2025/26 and 4,453 registered users. It issued 24,389 books, including renewals. That makes it the least used of Southend’s five branch libraries.

What residents said

The consultation ran from 28 August to 8 October. It drew 712 responses, 79 of them on paper. About 1,800 more people viewed the material without answering, which is how the council reaches its figure of more than 2,600.

The report says:

  • 471 respondents said a move to the college would affect them negatively or very negatively, against 110 who saw it positively
  • 554 raised concerns about relocating
  • 336 said they would be unlikely or very unlikely to use the library if it moved, against 198 who said they would
  • 98% said it was important or very important that the library stays accessible to people in the area
  • around a quarter reported a disability, long-term health condition or accessibility need

Their main worries about the college site were access for older people, families and people with mobility problems. They also cited the lack of a direct bus and the distance from local schools. Some saw benefits in a modern building shared with adult learning.

We covered the consultation when it closed in October, when campaigners disputed the repair bill.

What it means for you

  • Nothing changes yet. The library stays open in its current building while the council decides.
  • Watch the scrutiny meeting. The Place Overview and Scrutiny Committee meets on 3 December. Its views go to Cabinet.
  • The decision is due on 17 December. Cabinet will consider recommendations and “determine the next steps”, the council said.
  • Have your say through your councillor. The consultation has closed, but you can contact your ward councillor before the meetings.

Councillor Kevin Robinson, Cabinet Member for Planning, Property and Governance, said: “It is important to be clear that no decision has been made about the future of Southchurch Library.”

Sources