Cabinet approved taking out Three Shells Lagoon and restoring the beach for £800,000. Work could start in spring 2027 once planning and marine licences are granted.

Three Shells Lagoon is to be taken out completely and the beach restored, after Southend’s Cabinet approved the removal on Monday 16 November. Cabinet also set aside £800,000 for the work from the Structures budget in the council’s capital programme.

The decision notice was published on 18 November (Three Shells Lagoon decision). It is open to call-in by councillors until 24 November. If nobody calls it in, it takes effect on 25 November.

What Cabinet agreed

Cabinet resolved to:

  • approve the removal of the lagoon
  • let the Executive Director for Environment and Place, with the Cabinet Member for Business, Culture, Music and Tourism, prepare and submit the planning and marine licence applications
  • send the removal works through the council’s existing Infrastructure Term Service Contract
  • allocate the £800,000 from the Structures budget, money that is “held subject to viable business case”

The other two options, cutting a channel through the lagoon or cutting its steel walls down and capping them, were turned down. We set out all three, with their costs, before the meeting: officers recommend £800,000 removal.

Why it is going

The lagoon opened in July 2016 and cost about £1.95 million to build, according to the report to Cabinet. It has been fenced off since a safety incident earlier this year.

The decision notice says members heard about years of water quality problems, smells, safety concerns and maintenance costs. It says members “recognised the historic affection held by many residents for the lagoon”. But they accepted that repeated efforts to fix it had failed, and that keeping it would cost more with no guarantee the problems would end.

When the work could happen

The council needs planning permission and marine licences first. Subject to those, the decision notice says removal could begin in early to mid-spring 2027 and take 8 to 10 weeks. The timing has to fit seasonal limits set by the Marine Management Organisation and Natural England to protect wintering birds.

The rocks around the lagoon would be moved to East Beach for a sand dune restoration scheme planned for 2027/2028. The notice says rock for that scheme “often has to be imported from Norway”. The silt would stay under the sand already laid over it and disperse slowly, to avoid a plume reaching the saltmarsh and seagrass.

What it means for you

  • The lagoon stays fenced off until the work is done.
  • Three Shells beach is open. The decision notice points to the seafront’s paddling pools, which hold water at low tide.
  • You can have your say on the details. The planning and marine licence applications each carry their own public consultation, and we will report when they are lodged.

Sources