Cabinet's decision to remove Three Shells Lagoon for £800,000 has been called in by four councillors and is being reconsidered. It cannot take effect yet.
Updated 27 November: the call-in will be heard at Place Scrutiny on 3 December.
The decision to take out Three Shells Lagoon and restore the beach has been called in by four councillors, so it has not taken effect. Cabinet approved the removal, and £800,000 for it, on Monday 16 November.
The council’s decision page now gives the status as “Item Called In”. It says: “The decision is currently being reconsidered” (Three Shells Lagoon decision). The call-in window closed on 24 November. Had nobody used it, the decision would have taken effect on 25 November.
Who called it in, and why
The decision page lists four councillors:
- Cllr Alex Moyies
- Cllr Frankie Bird
- Cllr John Corrigan
- Cllr Stephen Harvey
All four gave the same reason. They say the Place Overview and Scrutiny Committee had chosen the lagoon for scrutiny before the decision, and put it on its work programme as “Pre-Cabinet Scrutiny” on 15 October. They write that there was not enough time for the committee to receive the Cabinet report before the decision was taken. As a result, they say, the committee “did not have the opportunity to look at the options, the £800,000 or the evidence for removal before the decision was taken.”
The call-in does not argue for keeping the lagoon. It is about the scrutiny committee getting to see the case first.
What Cabinet had agreed
Cabinet chose complete removal over two cheaper part-measures. The rocks around the lagoon would go to East Beach for a planned sand dune scheme, and the beach at Three Shells would be restored. Subject to planning permission and marine licences, the council said work could start in early to mid-spring 2027 and take 8 to 10 weeks. We set out the full decision when it was made: Three Shells Lagoon will be removed.
What happens next
The council’s issue page names the Place Overview and Scrutiny Committee as the scrutiny body for the lagoon (issue details). It will hear the call-in on Thursday 3 December. The agenda is now published, and the call-in is item 8 (Place Overview and Scrutiny Committee, 3 December). The meeting is at 6.30pm in Committee Room 1 of the Civic Suite, and it is webcast. The committee can let the decision stand or send it back to Cabinet.
The same meeting gets an update on the East Beach scheme that would reuse the lagoon’s rocks: restored dunes and a step-free boardwalk, costed at about £900,000.
What it means for you
- Nothing changes on the seafront for now. The lagoon stays fenced off, as it has been since a safety incident earlier this year.
- The spring 2027 start was never fixed. It already depended on planning permission and marine licences, and the call-in comes before either.
- Scrutiny meetings are public. You can attend at the Civic Suite.
We will report what the committee decides.
Have your say